sanborn boulevard – mitchell, sd

Project Details

Sanborn Boulevard Reconstruction – Mitchell, SD

  • West Havens Avenue to West 1st Avenue – this is a 5 block stretch of road in the heart of Mitchell.

Major Work Elements

  • Sanitary Sewer
  • Water Main
  • Storm Sewer
  • Concrete Paving
  • Sidewalk

 

Project Schedule

  • Start Date: March 2018
  • Estimated Duration: 80 days
  • Contract Completion Dates:
    • Substantial Completion: July 17, 2018
    • Final Completion: August 16, 2018

Update 6/29/18: Currently this project is approximately 70% complete with all of the main line paving finished.

 

Want to know more?

To be the absolute best at what we do, to always do quality work on time, and to be a positive force in the construction industry.
Our Values
We strive to provide the highest quality service to our customers, to provide a safe, stable and rewarding work environment for our employees, to provide leadership to our industry, and to attain a fair profit in the construction and construction service industries that we serve.

building people  ·  building  projects  ·  building futures

Email
Phone
Address
BX Civil & Construction
24663 475th Ave

Dell Rapids, SD 57022

Unable to display Facebook posts.
Show error

Error: Server configuration issue
Please refer to our Error Message Reference.

©BX Civil & Construction